Composed May
7th
Aquatic Center Votes
Monday's Cost
Operating Cost
Case Studies
Site Development
Project Costs
Opportunity Cost
Disclaimer
My Conclusion
References
Master
Plan
Monday's
Agenda
Agenda
Page
Web
Broadcast
TIF
Summary
TIF Map
|
|
The
council will vote to adopt the Huber
Heights Recreational Activity Center Master Plan.
This has also been referred to as the feasibility study. As a
master plan I would like to see better development of the expected
operating plan. In public sessions council has mentioned they
intend to hire the YMCA to administer the new complex. What
exactly does this mean? Is it possible Y membership will reduce
admission fees? The master plan mentions possible fee schedules but the
developer has gone out of their way to say these are still up to the
city
The Master Plan was put together by the
prospective Architectural firm. Whenever they have briefed during
public meetings they are careful to declare they will have nothing to do
with the operation of the facility and this aspect of the project is
totally up to the city. This leads to the question does the Master
Plan reflect at least in principle the City's expectation on fees and
revenues?
In public meetings council did state they have had preliminary
discussions with the Y and expect the Y will run the facility. I
am not aware of a formal agreement being disclosed in a public
forum.
During the May 4th Administrative Committee meeting the presentation
contained a wide range of net revenues for the operation of existing
facilities. One of the major differences was whether the cities
operated the facility themselves (bigger net revenues) or they
contracted out this job to another agency (marginal revenues or
loses). The Master Plan doesn't contain this information so I am
working from memory but of all the case studies sited only one city
realized the kind of net revenues presented in our Master Plan. Tip City
for instance has realized positive net revenue in only one year and that
profit was just $7000 |
|
I believe the council should disclose the intended operating plan
before they commit significantly more city resources to the
project. Is the intention for this project to provide additional
revenue to the city? Is there a scenario where the city will make
the facility free to residents? The Master Plan states charges
could be as high as $8.00 a person before the cost drives people
away. If the facility is built under capacity to start is $8.00 a
person the desired daily rate? Will Y membership be a factor in
determining rates?
Let me state again I am not currently a member of
council. I am not privilege enough to know what has been discussed
in executive session. There is also the possibility the
information is available publicly. I welcome you or present
council members to point to the public record if there is one available
and I will incorporate that knowledge in my assessment and decision
making process. The proposed fee schedule as well as expected
operating revenues/losses would moderately to significantly effect my
support for the project.
|